Vitality & Local weather CounselFoley Hoag LLP BOEM Pronounces Upcoming Wind Vitality Lease Public sale within the New York Bight; New York’s Subsequent Offshore Wind Solicitation to Observe


At this time, January 12, 2022, the Bureau of Ocean Vitality Administration (BOEM) introduced that on February 23, 2022 it is going to maintain a wind power lease public sale for six areas within the New York Bight (NY Bight), the coastal space between Lengthy Island and the New Jersey coast. BOEM’s issuance of the Ultimate Sale Discover (FSN) for the wind power lease areas comes simply days after New York State Governor Kathy Hochul introduced in her State of the State handle that the New York State Vitality Analysis and Growth Authority (NYSERDA) will subject its subsequent offshore wind solicitation following BOEM’s lease sale within the NY Bight. NYSERDA’s forthcoming solicitation, which the Governor acknowledged would search not less than 2,000 MWs of capability, will procure the renewable power credit from offshore wind tasks and is anticipated to incorporate the supply of $500 million in state funding for investments in wind port infrastructure and provide chain improvement.

BOEM’s public sale will enable offshore wind builders to bid on six lease areas comprising a complete of 488,201 acres. This space might host as much as 7 gigawatts of further offshore wind improvement within the NY Bight – sufficient to energy almost 2 million houses – and much more as know-how advances. The execution of any lease ensuing from the lease sale public sale would allow the successful bidder to maneuver ahead with project-specific plans to develop offshore wind power services inside the lease space. Such project-specific plans can be topic to subsequent environmental and technical opinions, public remark, and BOEM approval previous to improvement of the leased space.

Ultimate Wind Vitality Lease Areas

In June 2021, BOEM issued a Proposed Sale Discover (PSN) that recognized eight lease areas encompassing 627,331 acres (Figures 2a and 2b, under) for potential offshore wind improvement. Within the FSN, BOEM reoriented the eight originally-proposed lease areas and decreased the entire lease space by 22%, in the end arriving on the six last lease areas depicted in Determine 1. In accordance with the FSN, these modifications arose out of issues raised in feedback filed by ocean customers, the fishing business, the U.S. Coast Guard, navigation pursuits, the Nationwide Marine Fisheries Service, and the Division of Protection (DOD).

Determine 1, Ultimate Wind Vitality Lease Areas

Determine 2a, Proposed Wind Vitality Lease Areas

Determine 2b, Proposed Wind Vitality Lease Areas

Modifications to Lease Areas

BOEM faraway from leasing consideration proposed Lease Space OCS-A 0543, generally known as Hudson South A, as a result of issues raised by the fishing business and DOD. Ought to circumstances change in these areas, BOEM could rethink providing this space for lease in a future sale. BOEM additionally eliminated a number of areas that overlap with fishing exercise and seafloor options that could be doubtlessly delicate to impacts from offshore wind facility development. In accordance with the FSN, the removing of those areas decreased the viability of OCS-A 0540 (Hudson South D) as a standalone lease space, which led to the enlargement of the western boundary of OCS-A 0539 (Hudson South C) and removing of Hudson South D. By eradicating Hudson South A from consideration, the proposed “transit hall” between Hudson South A and Hudson South D was now not crucial. As its last reconfiguration of the proposed lease areas, BOEM eliminated the transit hall and expanded OCS-A 0541 (Hudson South E) and OCS-A 0542 (Hudson South F).

Modifications to Lease Stipulations

BOEM added a number of lease stipulations and refined a number of proposed lease phrases in response to stakeholder suggestions on the PSN. Notably, awarded leases can be restricted to 1 per bidder. Different new and refined stipulations intention to advertise engagement with tribes, ocean customers, underserved communities, different businesses, and stakeholders; flexibility in transmission planning; advances within the home provide chain; and the usage of mission labor agreements. For instance, lessees can be required to “make each affordable effort to enter a mission labor settlement protecting the development stage of any mission proposed for the Lease Areas.” Moreover, “BOEM is continuous a deliberate strategy to transmission and is evaluating choices together with the usage of cable corridors, regional transmission programs, meshed programs, and different mechanisms. Subsequently, BOEM could situation COP approval on the incorporation of such strategies the place applicable. BOEM encourages those that get hold of leases from this sale to have interaction in early coordination with adjoining lessees, states, Tribal Nations, and different ocean customers to establish methods to attenuate impacts from transmission. As well as, BOEM has modified the lease stipulations regarding communication with Tribal Nations and events to explicitly search enter and dialogue surrounding transmission easements previous to proposing such easements.”

What’s Subsequent?

Following its last public assembly on the NY Bight leasing course of on January 19, 2022, BOEM will maintain a mock public sale for 25 pre-qualified potential bidders on February 18, with the financial motion to be held on February 23. BOEM anticipates that the public sale will final one enterprise day, though it might go longer, and provisional winners of the lease sale can be introduced after the shut of the public sale.